Proposal Process

HRC  

   Yucca Mountain Research

The following is a brief outline of the process whereby tasks are funded under the Cooperative Agreement (Co-op).  It is not intended to be comprehensive and in some cases not all of the steps below may apply.

  1. Researchers affiliated with one or more institutions within the Nevada System of Higher Education (NSHE) identify an area of study related to Yucca Mountain.  The area of study may be anything related to nuclear waste, its disposal, or the proposed Yucca Mountain lrepository.  In order to maintain independence, researchers are expected to identify potential studies by reviewing published literature or by attending public meetings; researchers are discouraged from directly soliciting DOE personnel for ideas.  (See potential research for more information.)
  2. Researchers produce a concise white paper outlining the proposed work, its value to the Yucca Mountain Project, its intended duration, and the total annual budget.  This white-paper is submitted in electronic format to the Harry Reid Center (HRC) Cooperative Agreement Administrator for transmittal to the DOE contract office.  White-papers received by DOE, or its prime contractor, BSC, that were not properly submitted through the HRC will not be considered for funding under the Co-op.  (See white-paper guidelines for more information.)
  3. The HRC Cooperative Agreement Administrator forwards all white-papers to DOE; no grading of the white-papers, nor recommendations to DOE, are made by HRC personnel.
  4. A DOE merit review board meets periodically (usually no more than once a month) and reviews submitted white-papers.  If a white-paper is judged to have sufficient merit, and fits within budgeting and scheduling constraints, then a request for proposal (RFP) is drafted and sent to the HRC Cooperative Agreement Administrator for forwarding to the submitting researcher.  Please note:  The issuance of an RFP does not signify that a task has been approved for funding.
  5. The researcher then develops a detailed proposal which includes a detailed annual budget, a detailed schedule, a list of products to be produced and their due dates, the principal investigator (PI), equipment needed, etc... (See proposal guidelines for more information.)
  6. The proposal is then sent to the HRC Cooperative Agreement Administrator who forwards the proposal to DOE.
  7. The DOE Merit Review Board then reviews the proposal and determines whether or not to fund the task.
  8. If a task is funded, the DOE contracting office will notify the HRC Cooperative Agreement Administrator when the task is approved, when funds are available.
  9. After a task is approved, the PI and the NSHE/DOE Technical Liaison meet to finalize a milestone schedule.  This schedule is a more detailed schedule developed from the schedule submitted in the proposal.  These schedules, and progress towards meeting these schedules, will be posted on the internet for DOE and any other interested parties to view.
  10. Tasks personnel then undergo formal indoctrination and training.
  11. On a quarterly basis, each task is to submit a progress report which addresses, among other things, progress that has been made toward meeting the established schedule of activities.
  12. Tasks are expected to conduct work in accordance with approved budgets, schedules and workscopes.  Deviations must be approved in writing, by an authorized Department of Energy contracting officer.  Verbal or written approval from a DOE Technical Task Monitor is insufficient.
  13. In addition to quarterly reports, all tasks are expected, at a minimum, to submit a final technical report at the end of the task, and to maintain all data and related records that are generated under the task. 